56) The shearing of cohesive soil in drained test requires how many days?
- a) 1 to 2 days.
- b) 2 days.
- c) 2 to 5 days.
- d) 1 day.
Komal Bhandakkar Answered question January 5, 2021
Answer: c) 2 to 5 days.
Explanation:
- Since the soil in a drained test is sheared more slowly, the complete dissipation of pore pressure takes place & it takes nearly 2 to 5 days for shearing cohesive type of soil.
- The consolidated drained test is also called as a slow test or drained test, where the rate of application of loading is slowly and therefore the excess pore pressure is not developed within the sample.
Komal Bhandakkar Edited answer January 5, 2021